Book building inspections in Chilliwack
Chilliwack, British Columbia, Canada
Chilliwack, British Columbia, Canada. Book ordinary inspections before 3:30 p.m. at least one business day before they are needed. Large-project coordinated f
Key information
Book ordinary inspections before 3:30 p.m. at least one business day before they are needed. Large-project coordinated final or occupancy inspections need at least two business days. The eInspections service accepts requests around the clock.
On this page
Book the right inspection
Use eInspections online or call 604-793-2905 during business hours. Give the street address, permit/folder number and inspection type. Online availability does not remove the submission cutoff.
Large multifamily, commercial, industrial and institutional coordinated final/occupancy requests need two business days, plus the required confirmation and documentation binder.
Sources: Inspection booking lead times · Complete typical required inspection list
Keep the site ready
Post the fluorescent orange permit card where it is visible from the road. Keep approved plans available at every inspection. Written departmental approval is required before deviating from the plans or permit.
Footing forms must be approved before concrete is poured. Construction cannot continue beyond the foundation-form stage until the BC land surveyor’s certificate is submitted and approved.
Sources: Inspection booking lead times · Complete typical required inspection list
Complete the required stages
The table preserves every typical inspection named on the city list for single, two-family and townhouse work. Not every item applies to every project; the inspector and permit determine required stages.
Inspection readiness matters. Occupancy must be granted before the building is occupied. The city also states the building permit becomes void if construction has not begun within six months of issue.
Sources: Inspection booking lead times · Complete typical required inspection list
Key details at a glance
| Item | Details |
|---|---|
| Footing, including column/spot footings | Call for inspection at the relevant stage; confirm applicability with permit |
| Drain tile, rainwater distribution and damp proofing before backfill | Call for inspection at the relevant stage; confirm applicability with permit |
| Underslab/foundation insulation and vapour barrier before slab | Call for inspection at the relevant stage; confirm applicability with permit |
| Radon underslab rough-in | Call for inspection at the relevant stage; confirm applicability with permit |
| Underslab plumbing | Call for inspection at the relevant stage; confirm applicability with permit |
| Water, sanitary and storm services | Call for inspection at the relevant stage; confirm applicability with permit |
| Rough plumbing | Call for inspection at the relevant stage; confirm applicability with permit |
| Radon rough-in | Call for inspection at the relevant stage; confirm applicability with permit |
| Wood-burning chimney and fireplace | Call for inspection at the relevant stage; confirm applicability with permit |
| Framing and firestopping | Call for inspection at the relevant stage; confirm applicability with permit |
| Rain screen | Call for inspection at the relevant stage; confirm applicability with permit |
| Stucco lath/reinforcing before stucco | Call for inspection at the relevant stage; confirm applicability with permit |
| Insulation and vapour barrier | Call for inspection at the relevant stage; confirm applicability with permit |
| Final/occupancy before occupation | Call for inspection at the relevant stage; confirm applicability with permit |
Sources: Inspection booking lead times · Complete typical required inspection list
Steps to follow
- Choose required stage
Read the permit and full inspection list.
- Book within cutoff
Ordinary and coordinated-final lead times differ.
- Prepare site and plans
Do not pour, cover or occupy ahead of approval.
Sources: Inspection booking lead times · Complete typical required inspection list
Useful questions and answers
Can I request online after office hours?
Yes. eInspections accepts requests 24/7, but normal cutoffs still apply.
Source: Inspection booking lead times
What is the ordinary request cutoff?
Before 3:30 p.m. at least one business day before the inspection.
Source: Inspection booking lead times
How much notice does a coordinated large-project final need?
At least two business days.
Source: Inspection booking lead times
What information does a telephone request need?
Address, permit/folder number and inspection type.
Source: Inspection booking lead times
Where must the permit card be?
Posted at the job site and visible from the road.
Must plans be available to the inspector?
Yes. They must be on site for each inspection.
Can I pour footings before approval?
No. The forms must be inspected and approved first.
What is required before work goes beyond foundation forms?
A BC land surveyor’s certificate must be submitted and approved.
Can I change approved plans without written approval?
No. Written Building Department approval is required.
Can people occupy before the final occupancy approval?
No. Occupancy must be granted first.